11-22-24 - West North Bank Storm Sewer Project - Construction Update
11/22/2024
11-22-24 - West North Bank Storm Sewer Project - Construction Update
Construction will continue Monday through Friday 7am-6pm
- Storm line work will start on Springer Street on Monday November 25, 2024
- Hilton Road / Walnut Road will continue to be restricted.
- Monday November 25th after 8am - Due to water line relocation, the following areas will have a temporary water shut off while crews connect new water lines. 1-3 hr estimate time off. Water users will be advised if a boil advisory is needed once the water supply is restored.
- Hilton Rd
- 4780 to 4875 Walnut Rd
- All of Rosebraugh addition