Bridge / TAP status / Construction Sequence

7/7/2022

Bridge / TAP status 

  • Construction Sequence:

Phase 1        

  1. Construct median islands along State Route 79
  2. Construct Temporary pole to be utilized in Phase 2

Phase 2

  1. Demo the south bridge while maintaining traffic on north bridge
  2. Construct the proposed bridge
  3. Construct sidewalks on west side of State Route 79

Phase 3

  1. Demo north bridge / Traffic on new bridge
  2. Construct traffic signals
  3. Construct sidewalks on Mill Dam and in front of Wendy’s